ISO 22301 guide
ISO 22301 internal audit: how to plan, conduct and report an audit of your business continuity system
What clause 9.2 of ISO 22301 requires, how an internal audit differs from an exercise and from the 8.6 evaluation, a risk-based programme, tracing one activity from BIA to plan, and closing findings before Stage 2.
Key points
- ISO 22301 internal audit sits in clause 9.2: planned audits that tell management whether the business continuity management system meets your own requirements and the standard, and whether it is effectively implemented and maintained.
- An internal audit is not an exercise and not the clause 8.6 evaluation. Exercises test the capability, evaluation reviews the analysis and plans, and the audit checks that the whole system, including those two, works as designed.
- The audit that earns respect samples the chain from the business impact analysis to the plans, the exercises and the corrective actions, rather than reading the policy and the manual.
- The certification body's Stage 1 readiness review looks for internal audits that are planned and performed, so the first full audit has to be complete, reported and acted on before the Stage 2 audit.
What does ISO 22301 require of internal audit?
Clause 9.2 of ISO 22301:2019 has two parts: a general requirement (9.2.1) and a requirement for audit programmes (9.2.2). In plain terms, you audit your BCMS at planned intervals to find out two things. First, does it conform to what you decided for yourselves and to what the standard requires? Second, is it actually in place and kept up, not only written down?
The programme is yours to design, but it has to state how often audits happen, the methods, who is responsible, how audits are planned and how results are reported. It should take account of how important each process is and what earlier audits found. Each audit needs defined criteria and a defined scope. Auditors are chosen, and audits run, in a way that keeps them objective and impartial. Results go to the managers who need them, and documented information is kept as evidence that the programme ran and what it found.
Two other clauses complete the loop. Audit results are one of the inputs to the management review under clause 9.3, and every nonconformity the audit raises is handled under clause 10.1, Nonconformity and corrective action.
Internal audit, exercises and evaluation: three different checks
Business continuity has more self-checking built in than most management systems, and teams often confuse the three.
- The exercise programme (8.5) proves that strategies, plans and people work on a realistic scenario. Its output is a post-exercise report with actions. The guide to business continuity exercises covers how to design and run them.
- Evaluation of documentation and capabilities (8.6) asks whether the BIA, risk assessment, strategies, solutions, plans and procedures are still adequate and effective, at planned intervals, after an incident or invocation, and when something significant changes.
- Internal audit (9.2) stands one step back. It asks whether the exercises happened as planned, whether their actions were closed, whether the evaluations were triggered when they should have been, and whether every other clause is working.
So an exercise does not replace an audit, and an audit does not replace an exercise.
How to build an ISO 22301 audit programme
Start from risk, not from the clause list. The areas that carry the most weight in a BCMS are the business impact analysis, the selected solutions, the plans and the exercise record, because a weakness there means the organisation cannot recover when it has promised to. Those areas deserve earlier and deeper audits.
For a single-site organisation preparing for certification, a sound first cycle audits the whole scope at least once before Stage 2, often split into two or three sessions so process owners are not tied up for days. After certification, a rolling yearly programme is common. The table below shows what each area of the audit should sample.
| Area audited | What the auditor samples | Evidence that answers it |
|---|---|---|
| Context, scope and obligations (4) | Products, services and sites in scope against client and regulatory expectations | Scope statement, register of contractual and regulatory continuity requirements |
| Leadership and objectives (5, 6) | Authority to invoke plans; objectives with owners and dates | Policy, role assignments, objective tracking |
| Business impact analysis and risk assessment (8.2) | Two or three prioritised activities traced from impact criteria to MTPD, RTO and dependencies | BIA records signed off by process owners and management, risk assessment of disruption scenarios |
| Strategies and solutions (8.3) | Whether the alternate site, replicated data or second supplier exists in practice | Selection record, contracts, capacity tests, access lists |
| Plans, response and communication (8.4) | Contacts and succession checked against today's staff list | Plans under version control, call-tree results, stakeholder message templates |
| Exercises and evaluation (8.5, 8.6) | Exercises against the calendar; report actions closed; evaluation after the last change | Exercise calendar, post-exercise reports, evaluation records, updated plans |
| Competence and awareness (7) | Whether response teams know their role and how they will be reached | Training records, short interviews during the audit |
| Review and improvement (9.3, 10) | Previous findings closed with evidence and reviewed by management | Corrective action log, management review minutes |
Conducting the audit: sampling the chain of evidence
Plan and open
Send each auditee a short plan in advance: the criteria (the standard, your policy, the relevant plans), the scope, the times and the records you will ask for. ISO 19011:2026 is the reference for this method, from managing the programme to conducting each audit; its 2026 edition also gives more guidance on remote auditing and digital tools.
Trace, do not tick
The strongest technique in a BCMS audit is tracing a single prioritised activity end to end. Find its RTO in the BIA, the resources it needs, the solution chosen to meet that time frame, the plan that invokes the solution, the exercise that last tested it and the action raised afterwards. Every break in that chain is a candidate finding. A second trace on a supplier-dependent activity shows whether outsourcing sits inside the plans.
Write findings that stand on their own
Each finding states the requirement, the evidence observed and the gap between them,. For example: "The BIA sets an RTO of four hours for the claims line, but the selected alternate workspace needs a day to activate according to the provider's contract; no exercise has tested the switch." That is a finding a process owner can fix; "BCP needs improvement" is not.
Who should audit: competence and independence
ISO 22301 does not name a qualification for internal auditors. Clause 7.2 applies instead: you determine the competence the role needs, make sure auditors have it through education, training or experience, and keep evidence. For a BCMS, that means audit method plus enough BIA and exercise knowledge to spot a weak analysis.
Objectivity means auditors do not audit their own work. The business continuity coordinator should not audit the BIA they facilitated; an IT recovery lead should not audit the IT recovery plans. In a small organisation, cross-auditing between departments usually solves this. Certification auditors meet a separate standard, ISO/IEC TS 17021-6, which does not apply to your internal team.
How Sterling supports ISO 22301 internal audit
Trained auditors, a risk-based programme and findings closed before Stage 2.
Internal auditor training for your team is part of the engagement, as applicable to your standard, with practice on your own BIA and plans. Our expert and experienced consultants help you design the programme, can conduct the first full audit alongside your auditors, and make sure every finding is closed with evidence before the certification body arrives. Effivity, included with the engagement at no additional cost, holds the schedule, the findings and the corrective actions in one place. We ensure successful certification for our clients.
Book a free discovery callReporting, follow-up and the record auditors ask for
Keep the report short: scope and criteria, what was sampled, conclusions per area, and the findings with a grade. ISO 22301 prescribes no grading scheme, so many organisations mirror the certification body's language: a major nonconformity affects the system's ability to achieve its intended results, a minor one does not, and observations point to risk without a breach.
Each nonconformity then goes through correction, root cause and corrective action, with a check that the action worked. A fix to the BIA or a plan usually triggers an 8.6 evaluation, sometimes a new exercise. The certification body will ask to see the programme, audit plans, reports, the nonconformity and corrective action records, and management review minutes showing that results were considered. In Effivity, that record is in one place. Where the BCMS shares a management system with ISO/IEC 27001, one integrated audit can cover both; the guide to ISO 22301 and ISO/IEC 27001 explains how.
ISO 22301 internal audit: questions buyers ask
How often must we carry out ISO 22301 internal audits?
ISO 22301 requires internal audits at planned intervals and leaves the frequency to you. Most cover the full scope yearly and visit the BIA, prioritised activities and exercise record more often.
Can a business continuity exercise count as our internal audit?
No, an exercise tests the capability, while the internal audit checks the whole management system. The audit samples the exercise reports and their actions as evidence, but it must also cover leadership, objectives, competence, documentation, evaluation and corrective action.
Do we need a completed internal audit before the certification audit?
Yes, the certification body checks at the Stage 1 readiness review that internal audits are planned and being performed, and looks at their results at Stage 2. Aim to finish the first full audit, report it and take it to management review before Stage 2, with time to close the findings.
Do our internal auditors need a formal certificate?
ISO 22301 does not require a named auditor certificate; it requires competence that you define and can evidence. Training in audit method and business continuity, plus supervised audits, is the usual evidence.
Can our IT or risk team audit the BCMS?
Yes, provided they do not audit their own work. A risk team that facilitated the BIA should not audit it, and IT should not audit its own recovery plans; assign those areas to someone independent of them.
Can we outsource the ISO 22301 internal audit?
Yes, an external party can conduct your internal audit, but the programme, the follow-up and the corrective actions remain your responsibility. The certification body that will certify you should not be the one conducting it.
More ISO 22301 guides
Every guide in the ISO 22301 series is written for one question and links back to the hub for the whole picture.
- Business impact analysis: how to run one management will act on
- ISO 22301 certification process, step by step
- ISO 22301 certification cost: what moves the price
- ISO 22301 documentation: what you need and what you do not
- Effivity for ISO 22301: the guide
- Business continuity exercises: from walk-through to full invocation
- ISO 22301 internal audit: planning, conduct and reporting
- Ransomware recovery plan
- ISO 22301 requirements explained, clause by clause
- ISO 22301 vs ISO 27001
- ISO 22301 and ISO/IEC 27001: one system for security and continuity
Keep exploring
Explore more about ISO 22301
Watch a video on how to implement ISO 22301 here.
Watch a video on ISO 22301 requirements here.
ISO 22301 resources
Services for ISO 22301
Talk to a consultant
Plan a BCMS internal audit that holds up at Stage 2.
Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.
hello@sterling-grc.com+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page
What would you like to achieve?
Choose a starting point. The enquiry form takes about a minute.
Book my free discovery callContinue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice