ISO 22301 guide
ISO 22301 BIA and exercise planning checklist: the first BCMS cycle, step by step, with the evidence auditors look for
A 52-item working checklist for the continuity lead's first ISO 22301 cycle: preparing and running the business impact analysis, the risk assessment hand-off and strategy inputs, then the exercise programme, with eleven items weighted where audits most often find gaps.
Key points
- Fifty-two checks take a continuity lead through the first cycle of an ISO 22301 business continuity management system: preparing and running the business impact analysis, handing its results to the risk assessment and the strategy decisions, then planning, running and learning from the exercise programme.
- Each item names the record a certification auditor usually samples, so a tick means the evidence exists, not that a meeting was held.
- Eleven items carry double weight. In Sterling's experience these are where audits of a first BCMS most often raise findings: unapproved impact criteria, every activity rated critical, missing suppliers, time frames never compared with real capability, and exercise actions left open.
- This page is a working list for the person running the cycle, not a gap analysis or an audit. The method behind each step sits in the business impact analysis and exercises guides; an accredited certification body decides on certification, and Sterling does not certify.
How to use the BIA and exercise planning checklist
The list follows the order in which a continuity lead meets the work in year one, not the numbering of the standard. Clause 8.2, Business impact analysis and risk assessment, comes first because every later decision rests on it: the strategies and solutions in clause 8.3, the plans in clause 8.4, the exercises in clause 8.5 and the evaluation in clause 8.6. If the analysis is weak, each of those steps inherits the weakness.
Open three strands in the first fortnight, whatever else is happening. Ask top management to approve the impact criteria, because no workshop should start without them. Book process owners into the diary for the analysis sessions, because their availability sets the pace of the whole project. And pencil in the first exercise dates, because at least one exercise must have been run and its report acted on before the Stage 2 audit, and actions take weeks to close.
Tick an item only when the record beneath it exists and reflects how the organisation really works. The evidence lines are typical rather than complete; an auditor may ask for other records and will interview the people named in the analysis and the plans, not only the continuity lead. Items flagged as a common audit finding count twice in the progress score. The score measures how far preparation has gone; it does not forecast the outcome of an audit.
Your ticks stay in this browser on this device and nothing is sent to Sterling. Print the page or save it as a PDF to report progress to the management sponsor, and use Reset when a new cycle or a new site begins.
What this checklist is not
A list of ticks can look more reassuring than it should. Four limits apply.
- It is not the readiness check. Sterling's free online readiness check gives a quick view of where you stand before a project starts. This page is the detailed list used once the work is under way.
- It is not a gap analysis. Sterling's gap analysis, the first engagement stage, examines existing plans, recovery arrangements, exercise history and the people behind them, and returns actions with owners and dates. A checkbox cannot tell whether the recovery time a department quoted is achievable; a conversation with the people who would have to achieve it can.
- It is not a method guide. How to build impact criteria, run a workshop or design a scenario is explained in the two companion guides linked below. This page assumes you are using them.
- It is not the standard. Each line paraphrases a requirement or a common practice in plain English. ISO 22301:2019 with its 2024 amendment, available from ISO and national standards bodies, remains the reference.
Business impact analysis: how to run one management will act on
Business continuity exercises: from walk-through to full invocation
Before the first workshop: scope, sponsor and criteria
These items settle what the analysis covers and how severity will be judged. Skipping them is the most common reason a BIA has to be repeated.
Running the business impact analysis
Work outward from what the organisation delivers. The order below mirrors what clause 8.2 expects the analysis to produce.
Business impact analysis: how to run one management will act on
Handing the results to the risk assessment
The risk assessment is part of the same clause and starts where the analysis stops: it looks at what could disrupt the prioritised activities and the resources they need.
Preparing the strategy decision
Clause 8.3 belongs to management, but the continuity lead prepares the inputs. These items make sure the decision is taken on the analysis, not on a supplier's offer.
Planning the exercise programme
Plan the programme as soon as the first plans under clause 8.4 are drafted. Coverage, not frequency, is what an auditor tests first.
Running each exercise and reporting it
Use these items for every exercise, from the first plan walk-through to a full invocation.
Business continuity exercises: from walk-through to full invocation
Closing the loop: evaluation, audit and review
Clause 8.6 asks for the analysis, risk assessment, strategies, solutions, plans and procedures to be evaluated at planned intervals, after an incident or invocation and when significant change occurs. These items keep the first cycle from ending as a filed report.
What should exist at Stage 1, and be working by Stage 2
The certification body looks at the BIA and the exercise programme twice. Its Stage 1 readiness review asks whether the analysis and the programme are designed and documented; the Stage 2 audit asks whether they work, through interviews and records. The table sets a target for each part of this checklist at each point.
| Checklist section | Ready for Stage 1 (readiness review) | Working by Stage 2 (certification audit) |
|---|---|---|
| Set-up | Scope written; criteria approved; method documented | Scope matches what the auditor sees; criteria used consistently |
| Business impact analysis | Analysis complete and approved for every activity in scope | Owners can explain their ratings, time frames and dependencies in interview |
| Risk assessment | Register built on the prioritised activities; treatments decided | Treatments in place or on track; scenarios used in exercises |
| Strategy inputs | Options compared; management decision recorded | Solutions implemented and visible, not only purchased |
| Exercise programme | Coverage matrix and calendar approved | At least one exercise run and reported; the calendar is being followed |
| Running exercises | Exercise plan template and reporting format ready | Reports with measured outcomes; actions closed or progressing with dates |
| Evaluation and review | Internal audit and management review planned | Plans revised after exercises; audit and review completed and acted on |
If a row is short of the Stage 2 column, a later audit date is usually cheaper than a finding. The full sequence of the certification route and its timing are covered in their own guides.
ISO 22301 certification process, step by step
How Sterling supports the first BCMS cycle
An analysis management signs and exercises that change the plans, before the certification body arrives.
Sterling's expert and experienced consultants start with a gap analysis against this list, draft the impact criteria with your sponsor, facilitate the BIA workshops and help prepare the strategy decision. They then build the exercise programme from your risk assessment, facilitate the first exercises and help your teams write reports that lead to action. With Design™ your team does the work under our guidance; with Drive™ we manage it for you. Records sit in Effivity, included with the engagement at no additional cost. We ensure successful certification for our clients. The certificate is issued by the independent, accredited certification body you choose; Sterling does not certify.
Book a free discovery callBIA and exercise checklist: questions continuity leads ask
Can we start exercises before the BIA is finished?
A walk-through of an existing plan can run early and often exposes stale contact details and missing roles. Exercises meant to prove recovery objectives should wait until management has approved the time frames, otherwise there is nothing agreed to measure against.
How many exercises are needed before the certification audit?
The standard requires a programme at planned intervals rather than a fixed count. Before Stage 2, at least one exercise on a realistic scenario should have been run, reported and acted on, with the rest of the programme scheduled and visibly under way.
Is there an ISO standard on running exercises?
ISO 22398:2013, Guidelines for exercises, gives good practice for planning, conducting and improving exercises, and ISO lists it as current after its 2022 review. It is guidance, so the auditor assesses you against ISO 22301, not against it. ISO/TS 22317 plays the same guidance role for the business impact analysis.
Who should own this checklist?
The continuity lead or BCMS coordinator who runs the first cycle. Individual items belong to others: the sponsor approves criteria and results, process owners supply the analysis, management selects solutions and response teams take part in exercises.
We have several sites. Do we need one checklist per site?
Use one list for the system and an extra pass per site for the site-level items: activities, resources, dependencies, plans and exercises. Print or save a copy for each site so local managers track their own open items.
Where are our ticks stored?
Only in this browser on this device; nothing is sent to Sterling. During a Sterling engagement the BIA records, exercise reports and actions themselves sit in Effivity, so the evidence lives in one place.
More ISO 22301 guides
Every guide in the ISO 22301 series is written for one question and links back to the hub for the whole picture.
- Business impact analysis: how to run one management will act on
- ISO 22301 certification process, step by step
- ISO 22301 certification cost: what moves the price
- ISO 22301 documentation: what you need and what you do not
- Effivity for ISO 22301: the guide
- Business continuity exercises: from walk-through to full invocation
- ISO 22301 internal audit: planning, conduct and reporting
- ISO 22301 requirements explained, clause by clause
- ISO 22301 vs ISO 27001
- ISO 22301 and ISO/IEC 27001: one system for security and continuity
Keep exploring
Explore more about ISO 22301
Watch a video on how to implement ISO 22301 here.
Watch a video on ISO 22301 requirements here.
ISO 22301 resources
Services for ISO 22301
Talk to a consultant
Run your first BIA and exercise programme with an expert beside you.
Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.
hello@sterling-grc.com+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page
What would you like to achieve?
Choose a starting point. The enquiry form takes about a minute.
Book my free discovery callContinue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice