What clause 8.5 of ISO 22301 requires of an exercise programme, the five formats from plan walk-through to full invocation, a first-year calendar, how to design a scenario and write the post-exercise report an auditor will sample.

  • Updated September 2026
  • 8-minute read
  • Part of the ISO 22301 hub

Key points

  • ISO 22301 business continuity exercises are required under clause 8.5, Exercise programme: realistic scenarios with defined aims, run at planned intervals, each closed with a post-exercise report of outcomes, recommendations and actions.
  • A mature programme climbs a ladder, from a plan walk-through to a tabletop scenario, component tests, a simulation and, when the plans can bear it, a full invocation.
  • The exercise is only half the evidence. Clause 8.6 expects the BIA, strategies, plans and procedures to be evaluated afterwards and revised where the exercise exposed a weakness.
  • Auditors read the report, actions and revised plan together; a clean pass with no actions usually means the scenario was too easy.

What ISO 22301 requires of an exercise programme

A continuity plan that has never been exercised is a hypothesis. Clause 8.5 of ISO 22301:2019 exists to turn it into evidence. The organisation must exercise and test its strategies, solutions, plans and procedures, and the exercises must meet a few conditions that auditors check one by one:

  • Consistent with your objectives. Each exercise relates to the business continuity objectives set under clause 6.2, such as a recovery time objective for a prioritised activity.
  • Built on appropriate scenarios. The scenario is realistic for your context and each exercise has defined aims and objectives written before it starts.
  • Run at planned intervals. There is a programme, not a one-off event arranged before the certification audit.
  • Reported. Every exercise ends with a post-exercise report containing its outcomes, recommendations and actions for improvement.

Clauses 8.2 to 8.4 produce the BIA, the risk assessment, the solutions and the plans; clause 8.6 then requires them to be evaluated after exercises, incidents and significant change. An exercise puts the rest of clause 8 under load, and 8.6 records what the load revealed.

From walk-through to full invocation: the exercise formats

The standard does not prescribe formats. The five below are Sterling's recommended progression, ordered by how much of the real capability each one puts to work.

FormatWhat happensWho takes partWhat it proves
Plan walk-throughA team reads its plan step by step around a table and checks names, contacts, decisions and dependenciesOne response team and the plan ownerThe plan is current, complete and understood by those who must use it
Tabletop scenarioA facilitator describes a disruption as it unfolds; the team discusses decisions against the plan, without moving any resourcesResponse team, a management decision-maker, observersRoles, authority to invoke, escalation and communication hold together under time pressure
Component testOne element is operated for real: the call tree, a data restore, access to the alternate workspace, remote login at volumeThe technical or facilities owners of that elementA single solution delivers what the strategy assumed, measured against a recovery objective
SimulationA scenario runs in real time with injected events, and several teams act and communicate as they would on the daySeveral teams, senior management, sometimes key suppliersTeams coordinate, information flows, and the timeline of recovery is realistic
Full invocationThe plan is invoked: staff relocate or switch to the alternate arrangement and prioritised activities are delivered from itEveryone in the affected scope, with client and supplier coordination agreed in advanceThe capability works end to end at the capacity and within the time frames the BIA set

How to build an exercise programme that covers everything over time

Start from a coverage list, not a calendar: every plan, response team, site and solution selected under clause 8.3. Decide which format will exercise each item this year, and schedule harder formats only once easier ones are passed and their actions closed.

Add triggers to the fixed dates: a new site, a new outsourcing partner or a major system migration should prompt an exercise of the plans they affect.

A worked example: the first year for a two-site service operation

Consider a customer-service operation with two delivery sites, a prioritised activity with a four-hour recovery time objective and an alternate workspace agreed with a provider. A realistic first year looks like this:

QuarterExerciseObjective it checks
Q1Walk-through of each site's plan and the crisis communication procedurePlans are current; every named role is filled and reachable
Q2Tabletop scenario: loss of the main site on a weekday morningThe decision to invoke is taken by the right person within the agreed time
Q2Component tests: call tree out of hours, and a restore of client dataStaff are contacted within the target; data is recovered to the agreed point
Q3Relocation test: one team works a live shift from the alternate workspaceThe workspace delivers the minimum capacity the BIA requires
Q4Simulation across both sites with the telephony supplier taking partTeams, management and the supplier coordinate to meet the recovery time objective

The actions from each row feed the next, so the auditor sees a capability stretched, found wanting in places and improved.

Designing a scenario with aims, objectives and injects

Take the scenario from your own risk assessment under clause 8.2.3, not from the news. If the assessment rates a regional flood, a ransomware attack or the failure of a single-source supplier as the threats that matter, those are the scenarios that deserve rehearsal. Then write, before the day:

  • The aim, in one sentence: what the exercise is for.
  • Measurable objectives tied to the BIA: invoke within a stated time, resume the prioritised activity at its minimum level, reach named clients with an agreed message.
  • Injects: timed pieces of new information (a key person unavailable, a supplier not answering, media enquiries) that stop the team following the script too comfortably.
  • Evaluation criteria for observers, and control rules: who can stop the exercise and the limits that protect live operations.

Running the exercise day

Four roles keep an exercise rigorous. The facilitator runs the scenario and releases injects. The players respond as they would in a real disruption, using the plan. The observers record decisions, times and gaps against the evaluation criteria and do not intervene. The controller, often the same person as the facilitator in smaller exercises, protects live operations and can stop the exercise.

Close with a short, blame-free debrief while memories are fresh; people who fear judgement hide the weaknesses the exercise is meant to find.

The post-exercise report and what happens next

The report is the record clause 8.5 requires and the first thing an auditor samples. It states the scenario, aims and objectives; who took part; the outcome against each objective, with times measured; what went well; the weaknesses found; recommendations; and actions with owners and dates.

The actions then travel through the system. Changes to plans, contact lists and procedures are made under document control. Weaknesses in the BIA or the chosen solutions trigger the evaluation clause 8.6 requires. Failures against a requirement are handled as nonconformities under clause 10.1, with correction and corrective action. Exercise results are also an input to management review under clause 9.3, where resources that are still missing get a decision. The internal audit then checks that this chain was followed; our ISO 22301 internal audit guide covers how.

How Sterling runs your first exercises

Designed with your teams, observed independently, and acted on before Stage 2

Sterling's consultants build the exercise programme from your BIA and risk assessment, write the scenarios and injects, facilitate the first walk-throughs and tabletops, observe the component tests and help your teams write reports that lead to change. Exercises, reports and actions are recorded in Effivity, whose business continuity module supports drills, tests and tabletop exercises, so the evidence is in one place when the auditor asks. Under Sustain™, we keep facilitating exercises after certification. We ensure successful certification for our clients.

Book a free discovery call

Where exercise programmes go wrong

  • Only the IT recovery is tested. A data restore proves the RPO, not that people can deliver the service. Business teams need exercises of their own.
  • The scenario is written to be passed. An exercise with no weaknesses found teaches nothing and persuades no auditor.
  • Actions are recorded and forgotten. Open actions from last year's report are a finding waiting to happen.
  • Suppliers stay outside. Where a prioritised activity depends on a provider, its role belongs in at least one exercise.
  • Results never reach the BIA. When an exercise shows a recovery objective cannot be met, either the solution or the objective must change; our business impact analysis guide explains how to revisit it.

ISO 22301 business continuity exercises: questions buyers ask

How often should ISO 22301 business continuity exercises be run?

As often as your programme plans, because the standard requires exercises at planned intervals rather than fixing a number. Most organisations exercise something every quarter and ensure every plan and critical solution is exercised at least once in a year, with extra exercises after significant changes.

What is the difference between an exercise and a test?

An exercise develops and checks how people use the plans in a scenario, while a test checks that a specific solution works against a pass or fail measure. A tabletop is an exercise; a timed data restore or a call-tree run is a test. A balanced programme needs both.

Does a real disruption count as an exercise?

A real invocation does not replace the planned programme, but it is valuable evidence of capability. Clause 8.6 requires an evaluation after an incident or invocation, and its lessons should reshape the next exercises. Record it with the same rigour as a post-exercise report.

Who should take part in a business continuity exercise?

The people named in the plan being exercised, including the manager with authority to invoke it. Add observers who are not playing, and involve key suppliers or outsourced providers when a prioritised activity depends on them.

What will the certification auditor look for in our exercises?

The auditor looks for a planned programme, scenarios linked to your risks and objectives, post-exercise reports with measured outcomes, and evidence that the resulting actions changed the plans, the BIA or the solutions. Our ISO 22301 certification process guide explains where this falls in Stage 1 and Stage 2.

ISO 22301 implementation

ISO 22301 requirements

Get the document

We e-mail the document as a PDF link. Tell us who you are and where to send it.

A quick security check confirms the request comes from a person.

By requesting the document you agree to our privacy notice. Sterling uses these details to send it and to respond to your request. We never sell your data.

Talk to a consultant

Build an exercise programme that proves your continuity plans work.

Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.

hello@sterling-grc.com

+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page

What would you like to achieve?

Choose a starting point. The enquiry form takes about a minute.

Your goal
Book my free discovery call

Continue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice