ISO/IEC 27001 implementation plan: the phases, the owners, the deliverables and the decision points
Clause by clause: ISO/IEC 27001:2022 requirements: every clause explained →
Eight phases take a single-site ISO/IEC 27001 programme from kick-off to the certification decision in four to eight months. Here are the weeks, deliverables, owner and decision point of each phase, the five roles, and what changes between Design™ and Drive™.
Key points
- A workable ISO/IEC 27001 plan gives every phase one owner, checkable deliverables, a week range and the management decision that closes it.
- Technical controls and the records they must accumulate before Stage 2 set the pace, not policy writing.
- Risk owners approve treatment and accept residual risk; the sponsor fixes scope, criteria and policy. Neither decision belongs to IT.
- Design™ and Drive™ are alternative levels of Sterling support for one plan; either way, your managers decide.
How to run ISO/IEC 27001 as a project
Run certification as a project of eight phases: scope and context, risk assessment and treatment, the Statement of Applicability, control implementation by Annex A theme, documentation, awareness, internal audit with management review, and the certification audits. For each, fix the accountable person, the output, the weeks and the management decision the next phase depends on. Overlapping phases fit the four to eight months a single-site programme needs.
The standard requires no project plan, yet clause 6.1.3 requires a risk treatment plan the risk owners approve, and clause 6.2 requires you to decide what will be done to meet your security objectives, with what resources, by whom, by when and how results will be evaluated. Your plan carries both and starts where ISO/IEC 27001 gap analysis: what it covers and what you get ends.
The eight phases: weeks, deliverables, owners and decision points
Bracketed weeks are for an eight-month programme that must first build logging, access management, backup or supplier assurance.
| Phase | Weeks: four-month (eight-month) plan | Deliverables | Owner | Decision point |
|---|---|---|---|---|
| 1. Scope, context and gap analysis | 1 to 2 (1 to 4) | Target window; scope naming services, sites, systems, cloud platforms and interfaces; issues and interested parties, climate change considered; gap report and action plan | Sponsor and ISMS lead; Sterling runs the gap analysis | Sponsor fixes scope, target window and people's time |
| 2. Risk assessment and treatment | 2 to 5 (3 to 8) | Risk and acceptance criteria; asset inventory; risk register; dated treatment plan | ISMS lead facilitates; risk owners decide | Sponsor approves criteria and tooling; risk owners approve the plan and accept residual risk |
| 3. Statement of Applicability | 4 to 5 (7 to 10) | All 93 Annex A controls, each justified as included or excluded, with implementation status | ISMS lead | Sponsor approves version 1 as the build list |
| 4. Control implementation by Annex A theme | 3 to 7 (5 to 18) | Controls running in all four themes; vulnerability assessment, fixes and retest; first access review, restore test and supplier assessments | IT, HR and facilities owners | Risk owners sign off treatments; sponsor appoints the certification body |
| 5. Documentation | 3 to 8 (4 to 18) | Information security policy; topic-specific policies and procedures where needed; document control | ISMS lead; control owners approve procedures | Top management approves the policy |
| 6. Awareness and competence | 6 to 9 (12 to 20) | Awareness for everyone in scope; competence records for security roles; internal auditors trained | HR owner | Sponsor appoints the internal auditors |
| 7. Internal audit and management review | 10 to 12 (22 to 26) | Audit of clauses 4 to 10 and applicable controls; corrective actions; review minutes | Internal auditor; sponsor chairs the review | Management review: Stage 1 now, or not yet |
| 8. Certification | 13 to 18 (27 to 35) | Stage 1 readiness review, its concerns closed; Stage 2; responses to nonconformities | ISMS lead | The certification body decides, independently |
Phases 2 to 6 overlap on purpose. Controls leave records from the day they go live and phase 7 samples them, so the stretch from the last significant control to Stage 2 cannot be squeezed; ISO/IEC 27001 timeline: how long certification takes, stage by stage gives our working rule. Appoint the certification body during phase 4, since Stage 1 is normally booked four to eight weeks ahead. After the decision the plan becomes the ISMS calendar, kept running under Sustain™.
The roles: sponsor, ISMS lead, risk owners, IT and HR owners, internal auditor
Three clauses shape the team: 5.3 has top management assign responsibility for the ISMS conforming to the standard and for reporting its performance, 6.1.2 requires risk owners to be identified, and 9.2 requires auditors selected so that audits are objective and impartial.
- Sponsor. From top management: owns the target window, provides resources, approves policy and risk criteria, and chairs the management review. Stage 2 auditors test that commitment in interview.
- ISMS lead. Runs the plan weekly, facilitates the risk workshops and keeps the Statement of Applicability and evidence in order. Agree this person's project time in writing; it erodes first.
- Risk owners. Managers accountable for a service, process or platform, who choose treatments and accept what remains. A register where IT owns every risk shows the business stayed out.
- IT and HR owners. IT carries most technological and many organisational controls; HR carries screening, terms of employment, leavers and awareness records; facilities takes the physical theme.
- Internal auditor. A trained colleague from another function, a group auditor or an external one, never auditing their own work; ISO/IEC 27001 internal audit: planning, conduct and reporting explains how to run it.
Design™ or Drive™: two levels of support, one plan
Every Sterling engagement runs on Sterling OS™, our delivery operating system, with a choice of two levels of support. They are alternatives, not consecutive steps; the phases and decisions above stay the same. Under Design™ your team implements with Sterling's structure and coaching; under Drive™ Sterling consultants take on the agreed consulting and documentation work.
| Work in the plan | Design™ | Drive™ |
|---|---|---|
| Risk register and Statement of Applicability | Your ISMS lead completes them after Sterling workshops; Sterling reviews | Sterling facilitates and drafts; your risk owners decide |
| Policies and procedures | Your owners draft on Sterling templates; Sterling reviews | Sterling drafts with each owner, who approves |
| Controls in daily operation | Your IT, HR and facilities owners | The same, with Sterling checking the evidence |
| Chasing actions between sessions | Your ISMS lead | Mainly Sterling consultants |
| Decisions in the phase table | Your sponsor and risk owners | The same |
Design™ suits an ISMS lead with time and IT and HR teams with capacity; Drive™ suits a contractual deadline, a thin team or several platforms. The operating weeks are the same on both.
Five mistakes that stall ISO/IEC 27001 projects
- A scope still open in week six. While leadership debates whether a client-dedicated environment or an offshore support desk is in, the risk assessment waits; see ISO/IEC 27001 scope: boundaries, interfaces and the mistakes that cost you.
- A risk method nobody can finish. Unagreed criteria or thousands of asset and threat pairs leave the Statement of Applicability without a basis. Agree criteria in the first fortnight and group assets by service.
- Security handed to IT. Leavers, visitors and business risk decisions go unowned until an auditor notices. Name an owner for each Annex A theme at kick-off.
- Policies ahead of controls. A policy promising quarterly access reviews becomes a finding when none has been held. Write each policy as its control goes live.
- Tooling decided late. Logging or single sign-on procured in week ten delays every later phase; settle tools at the phase 2 decision.
How Effivity holds the plan and the evidence
Plans kept in spreadsheets drift from their evidence, and each audit sample becomes a search. In a Sterling engagement both sit in Effivity, the Sterling group's ISO and GRC automation platform, used in 50+ countries, configured by your consultant within the agreed scope and included with the engagement, at no additional cost.
It holds the plan (actions with owners, due dates, reminders, escalation and a sponsor dashboard), the ISMS itself (scope, assets, risk register, Statement of Applicability, versioned policies) and the evidence (access reviews, incidents, supplier assessments, awareness records, vulnerability findings, internal audits, management review). Auditors then sample records where they were created; Effivity for ISO/IEC 27001: the guide covers the set-up.
How Sterling runs your ISO/IEC 27001 plan
Phases dated from your deadline, owned by your people, held in Effivity.
Sterling's gap analysis ends in your plan, dated back from your client's or tender's deadline. You choose Design™ or Drive™; the vulnerability assessment, internal auditor training and complimentary awareness training for your people, through preferential Sterling Academy access, sit in the same plan as part of the engagement. Before you commit, a Sterling consultant can phase a plan around your services, systems, sites and deadline, free and yours to keep. We ensure successful certification for our clients. Sterling does not certify: an independent, accredited certification body of your choosing audits and decides.
Book a free discovery callISO/IEC 27001 implementation plan: questions buyers ask
Should our IT manager be the ISMS lead?
It can, if the role carries authority beyond IT and protected time; otherwise risk, HR and supplier decisions drift to one team. Many organisations choose a compliance, risk or operations manager instead.
Can the ISMS lead also carry out the internal audit?
Not of work they designed or run, because clause 9.2 requires objective, impartial audits. Use a trained colleague from another function or an external auditor; in a Sterling engagement the internal audit is conducted or facilitated as agreed.
What if a treatment action cannot be finished before Stage 2?
The Statement of Applicability shows whether each necessary control is implemented, and the treatment plan its owner and date. Auditors can usually accept approved work in progress; a control declared as operating with no record behind it is another matter.
Can the same plan prepare us for SOC 2 as well?
Largely: map controls and evidence once. SOC 2 adds milestones of its own, including the system description, the trust services criteria in scope and, for Type 2, an examination period the service auditor tests; ISO/IEC 27001 vs SOC 2: which one, or both? compares the two.
A client asks us to add a platform mid-project. What changes?
Treat it as a planned change under clause 6.3: the platform needs assets, risks, a Statement of Applicability review and weeks of evidence. Tell the certification body, since audit time follows scope; if Stage 2 would slip past your client's date, certify the original boundary first and extend later.
More ISO/IEC 27001 guides
Every guide in the ISO/IEC 27001 series is written for one question and links back to the hub for the whole picture.
- Annex A: the 93 controls by theme, explained
- ISO/IEC 27001 certification cost: what moves the price
- ISO/IEC 27001 gap analysis
- ISO/IEC 27001 for government suppliers and public bodies
- ISO/IEC 27001 for healthcare and health-data processors
- ISO 27001 certification in India
- Integrating ISO/IEC 27001 with ISO/IEC 27701 and ISO 22301
- ISO/IEC 27001 internal audit: planning, conduct and reporting
- ISO/IEC 27001 requirements explained, clause by clause
- ISO/IEC 27001 risk assessment and treatment, step by step
- The Statement of Applicability: how to write one that survives the audit
- ISO/IEC 27001 vs SOC 2: which one, or both?
Keep exploring
Explore more about ISO/IEC 27001
Watch a video on how to implement ISO 27001 here.
Watch a video on ISO 27001 requirements here.
ISO/IEC 27001 resources
Services for ISO/IEC 27001
Talk to a consultant
Plan your ISO/IEC 27001 certification with confidence.
Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.
hello@sterling-grc.com+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page
What would you like to achieve?
Choose a starting point. The enquiry form takes about a minute.
Book my free discovery callContinue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice