What ISO/IEC 17025 requires about measurement uncertainty, how to build a budget step by step, an illustrative worked example, how decision rules use uncertainty, and the record an accreditation body's assessors expect to reconstruct.
Key points
- ISO/IEC 17025 gives measurement uncertainty its own clause, 7.6 Evaluation of measurement uncertainty, and ties it to traceability, methods, the validity of results and reporting.
- A defensible budget names the measurand, lists every significant source, shows where each number came from and combines them in a way another metrologist could repeat.
- Uncertainty matters most when you state that an item passes or fails: the decision rule agreed at contract review decides how the uncertainty is taken into account.
- Assessors test the budget against the bench: the certificates, validation data, control charts and proficiency testing results must support every figure in it.
What does ISO/IEC 17025 ask about measurement uncertainty?
ISO 17025 measurement uncertainty work starts with one question: how far from the true value could this reported result reasonably be? The standard answers the "whether" in clause 7.6, Evaluation of measurement uncertainty, which sits among the process requirements next to method selection, technical records and ensuring the validity of results. It leaves the "how" to the laboratory.
Uncertainty also depends on other clauses, and an assessor will follow those threads:
- 6.5 Metrological traceability. The uncertainty stated on your reference standards' calibration certificates is usually the first line of a calibration budget.
- 7.2 Selection, verification and validation of methods. Verification and validation data supply repeatability, reproducibility and bias figures.
- 7.7 Ensuring the validity of results. Control charts and proficiency testing show whether the claimed uncertainty holds up in routine work.
- 7.8 Reporting of results. Test reports (7.8.3), calibration certificates (7.8.4) and statements of conformity (7.8.6) are where uncertainty reaches the customer.
The edition in force is ISO/IEC 17025:2017, confirmed in 2023 with no amendment. Method validation itself is covered in our method verification and validation guide; this page stays with the uncertainty that follows from it.
How to build an uncertainty budget, step by step
An uncertainty budget is a table that turns a list of doubts into one number with a stated confidence.
1. Define the measurand
State exactly what is being measured, under which conditions and by which method. "Temperature indicated by a digital thermometer at 100 °C in a stirred liquid bath" is a measurand; "thermometer accuracy" is not.
2. Write the measurement model
Express the result as an equation of its inputs, even a simple one such as error = indicated value minus reference value plus corrections. The model shows which inputs carry uncertainty and how strongly each one moves the result.
3. List the sources
Work through reference standards, their drift, the environment, the item's resolution, the operator, sampling and sample preparation, and repeatability. A cause-and-effect sketch drawn with the analysts helps.
4. Quantify each source
Some contributions are evaluated statistically from repeated observations (often called Type A); others come from certificates, specifications, manufacturer data or experience (Type B). Each is converted to a standard uncertainty by dividing by the factor that suits its distribution.
5. Combine and expand
Independent standard uncertainties, each multiplied by its sensitivity coefficient, are combined as the square root of the sum of squares. The combined figure is then multiplied by a coverage factor to give the expanded uncertainty that appears on the report.
6. Challenge the result
Compare the expanded uncertainty with the spread of your control chart and your proficiency testing performance. A budget smaller than the scatter you actually see has missed something.
A worked example: calibrating a digital thermometer (illustrative)
The figures below are illustrative only: a budget for comparing a digital thermometer with a reference thermometer in a liquid bath at one point, 100 °C. Your own values must come from your own evidence.
| Contribution | Where the value comes from | Value and distribution | Standard uncertainty (°C) |
|---|---|---|---|
| Reference thermometer calibration | Its calibration certificate: expanded uncertainty 0.04 °C at k = 2 | 0.04 °C, normal, divide by 2 | 0.020 |
| Reference drift between calibrations | The reference's own calibration history | ±0.03 °C, rectangular, divide by √3 | 0.017 |
| Bath uniformity and stability | The laboratory's bath characterisation record | ±0.05 °C, rectangular, divide by √3 | 0.029 |
| Resolution of the thermometer under calibration | Display resolution 0.1 °C, half-interval 0.05 °C | ±0.05 °C, rectangular, divide by √3 | 0.029 |
| Repeatability | Ten readings, standard deviation 0.04 °C, uncertainty of the mean | 0.04 °C divided by √10, normal | 0.013 |
| Combined standard uncertainty | Root sum of squares, all sensitivity coefficients 1 | 0.050 | |
| Expanded uncertainty | Coverage factor k = 2 | 0.10 |
The bath and the resolution outweigh the reference thermometer, so a better reference would barely change the result. The repeatability term is small only because ten readings were averaged; if routine calibrations use three readings, the budget must say three.
Uncertainty in testing laboratories
Chemical, microbiological and materials testing rarely suits the neat component-by-component model above. Sample heterogeneity, matrix effects and analyst technique interact. Many testing laboratories therefore work "top down", building the estimate from data they already hold:
- within-laboratory reproducibility from long-term quality control results, covering different days, analysts and equipment;
- bias, estimated from certified reference materials, spiked samples or proficiency testing results;
- any significant source those data do not capture, such as sampling in the field or a sub-sampling step, added separately.
The approach is only as strong as the data behind it. With only a few months of control results, say so and revisit the estimate as data accumulate. Proficiency testing and interlaboratory comparison, which feed this evidence, have their own guide.
Uncertainty, decision rules and statements of conformity
When a measured value sits close to a limit, its uncertainty interval can straddle that limit, and the answer "pass" may be wrong. The 2017 edition dealt with this by introducing the decision rule: the laboratory agrees with the customer, during the review of requests, tenders and contracts (7.1), how uncertainty will be accounted for, and then reports statements of conformity (7.8.6) in line with that rule.
The usual choice is simple acceptance, comparing the value directly with the limit, or guarded acceptance, where a guard band derived from the uncertainty narrows the limit so a "pass" is less likely to be false. Published guidance on decision rules, such as ILAC G8, is widely used; now that ILAC's work has moved to Global ACI, confirm with your accreditation body which guidance document and edition it expects you to refer to.
Whatever rule is chosen, three things must be traceable in the record: the rule agreed, the customer's agreement, and the uncertainty used when the statement was made.
What the uncertainty record should contain
Assessors check whether the number on the report can be reconstructed and defended. A complete record for each method and range usually holds:
- the measurand, the method reference and the range the budget covers;
- the measurement model and the list of sources considered, including those judged negligible and why;
- the value, distribution, divisor and origin of each contribution, with the certificate, characterisation or data set it came from;
- the combined and expanded uncertainty, the coverage factor and the rounding applied when reporting;
- the author, the reviewer, the date, and the triggers for revision: a new reference standard, a changed method, new equipment, a move of premises or a poor proficiency testing result.
If the budget lives in a spreadsheet, treat that spreadsheet as part of your controlled information: locked formulas, a check calculation and a version history.
Mistakes that weaken an uncertainty budget
- Copying the certificate uncertainty as the whole answer. The reference standard's uncertainty is one input; the laboratory's own process adds to it.
- Double counting or dividing twice. An expanded uncertainty taken from a certificate must be divided by its own coverage factor before it enters the budget.
- One budget for every range. Resolution, drift and environment behave differently at the ends of a range.
- A budget nobody revisits. A change of reference, method or location that leaves the budget untouched is an easy finding.
- An uncertainty smaller than the evidence allows. A claim tighter than the control chart or proficiency testing results invites a technical assessor's questions at once.
For the wider list of what goes wrong at assessment, see our guide to the ten common mistakes.
How Sterling builds uncertainty evidence
Budgets your analysts understand and your assessor can reconstruct.
Our expert and experienced consultants work method by method with your technical staff: defining each measurand, identifying the sources, gathering the certificates and data behind every figure, and setting the decision rule into contract review. The budgets stay in your own tools, so your people can maintain them. The management system records around them live in Effivity, used in 50+ countries and included with the engagement, at no additional cost. We ensure successful accreditation for our clients. Sterling does not accredit: the accreditation body assesses the laboratory and decides.
Book a free discovery callISO 17025 measurement uncertainty: questions buyers ask
Do testing laboratories need measurement uncertainty under ISO 17025, or only calibration laboratories?
Both do: clause 7.6 sits in the process requirements that apply to every laboratory activity on the scope. How rigorous the evaluation can be depends on the method, and testing laboratories often build their estimates from validation and quality control data rather than a component-by-component model.
How often should an ISO 17025 uncertainty budget be reviewed?
Review it whenever something that feeds it changes, such as a new reference standard, method, piece of equipment or location, and otherwise on a planned interval the laboratory sets for itself. A poor proficiency testing result is also a trigger.
What coverage factor should we use for expanded uncertainty?
Most laboratories report with k = 2, which for a normal distribution corresponds to roughly 95% coverage. With few data or one dominant non-normal contribution another factor may be justified; record the reasoning.
Can we reuse an uncertainty budget from another laboratory or a published method?
You can use one as a starting structure, but not its numbers. Repeatability, environment, equipment and reference standards are specific to your laboratory, so every contribution must be replaced with your own evidence.
Who in the laboratory should own the uncertainty budgets?
The technical staff authorised for each method should build and maintain them, with review by the technical manager or another competent person. Staff who own the budgets can explain them at assessment.
More ISO/IEC 17025 guides
Every guide in the ISO/IEC 17025 series is written for one question and links back to the hub for the whole picture.
- ISO/IEC 17025 accreditation process, step by step
- ISO/IEC 17025 accreditation cost: what moves the price
- ISO/IEC 17025 documentation: what you need
- Effivity for ISO/IEC 17025: the guide
- ISO/IEC 17025 internal audit: the technical clauses
- ISO 9001 vs ISO/IEC 17025: what accreditation adds
- ISO 17025 management review
- Measurement uncertainty under ISO/IEC 17025: a budget you can defend
- Method verification and validation under ISO/IEC 17025
- ISO 17025 accreditation in the Netherlands and Europe
- ISO 17025 nonconformities
- ISO/IEC 17025 requirements explained, clause by clause
Keep exploring
Explore more about ISO/IEC 17025
Watch a video on how to implement ISO 17025 here.
Watch a video on ISO 17025 requirements here.
ISO/IEC 17025 resources
Services for ISO/IEC 17025
Talk to a consultant
Build measurement uncertainty budgets your laboratory can defend at assessment.
Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.
hello@sterling-grc.com+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page
What would you like to achieve?
Choose a starting point. The enquiry form takes about a minute.
Book my free discovery callContinue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice