What clause 9.3 of ISO/IEC 27001:2022 requires top management to review and decide, how often to meet and who attends, a 90-minute quarterly agenda, how decisions reach the risk register and the Statement of Applicability, and the minutes auditors read.
Key points
- Clause 9.3 of ISO/IEC 27001:2022 requires top management to review the ISMS at planned intervals, consider a defined set of inputs and decide on improvement and on changes to the system.
- Its inputs include interested parties' changing needs and expectations, new in 2022, and the risk assessment results with the treatment plan's status.
- Auditors read the minutes, then test them: who attended, what was considered, what was decided, who owns each action and where each decision went next.
- Sterling recommends a 90-minute quarterly review on a fixed agenda, chaired by top management, instead of one annual ceremony staged for the auditor.
What clause 9.3 requires of top management
Management review is where the people who run the organisation, not the security team, judge what the ISMS has delivered and decide what changes. ISO/IEC 27001:2022 places it in clause 9, Performance evaluation, in three parts: 9.3.1 General, 9.3.2 Management review inputs and 9.3.3 Management review results. Top management reviews the ISMS at planned intervals to confirm it remains suitable, adequate and effective. We paraphrase below; the standard's text governs.
The inputs, by topic
- whether actions from earlier reviews were completed;
- changes in the internal and external issues affecting the ISMS;
- changes in interested parties' needs and expectations, added in 2022;
- security performance, as trends in nonconformities and corrective actions, monitoring and measurement results, audit results and progress on objectives;
- what clients, regulators, staff and other interested parties are saying;
- risk assessment results and progress on the treatment plan;
- opportunities to improve.
The climate change question added by Amendment 1:2024 is best revisited under the second item.
The outputs
The 2022 edition calls them results and the 2013 edition called them outputs, but the substance is unchanged: decisions about where to improve and about any changes the ISMS needs, evidenced by documented information. Resources are not listed separately; funding a treatment or a role is a change to the ISMS, and clause 5 already makes resources top management's responsibility.
How often to hold it, and who must attend
The standard leaves the interval to you, so the first evidence is a plan: dates for the year, set in advance and kept. Annual can suit a small, stable scope, but most ISMSs change every quarter, so we recommend quarterly reviews plus an extra sitting after significant change, such as an acquisition or a serious breach.
Top management is the person or group that directs and controls the organisation, or the part the ISMS covers, at the highest level. The chief executive or managing director chairs, with the leaders who own the services in scope; the ISMS lead prepares the pack, and IT, HR, legal and the lead who answers client questionnaires join for their items. An IT steering group can prepare the review but cannot replace top management.
One 90-minute meeting a quarter: a sample agenda
A yearly review drifts into ceremony: a long deck built for the auditor. Instead, keep the inputs in the same order every quarter, send a pack of one page per item a week ahead, show trends, and ask each presenter for a proposal.
| Agenda item | What is brought to the meeting | Presenter | Minutes |
|---|---|---|---|
| 1. Earlier actions | Closed with evidence, late with a new date, or withdrawn with a reason | ISMS lead | 10 |
| 2. Context and interested parties | Changes in services, suppliers and sites; new contract, regulatory and questionnaire demands; client and staff feedback | ISMS lead; legal or commercial lead | 15 |
| 3. Performance and objectives | Trends in the agreed measures, such as patching, access reviews and restore tests; progress on objectives | IT lead; objective owners | 15 |
| 4. Incidents and nonconformities | Trends, causes, repeats; corrective actions verified or overdue | ISMS lead | 10 |
| 5. Audit results | Internal, certification body and client audit findings; vulnerability assessment results and remediation | Internal audit lead | 10 |
| 6. Risk and treatment | New assessment results, risks above criteria, late treatments, accepted residual risks, Statement of Applicability changes | Risk owners | 15 |
| 7. Improvement and decisions | Proposals from staff, audits and incidents; decisions on improvements and ISMS changes, each with an owner and a date, read back | Chair | 15 |
Once a year, also confirm that the scope and policy still fit, set objectives and agree the audit programme. Running ISO 22301 or ISO/IEC 27701 too? One review can cover each standard's inputs; see our integration guide.
How the review connects to the risk assessment and the Statement of Applicability
The risk input turns a performance report into governance. Clause 8.2 requires risk assessments at planned intervals and on significant change, and refreshing the register before each review keeps the figures current. Under clause 6.1.3, risk owners approve the treatment plan and accept residual risk; the review should see what they accepted, challenge anything above the criteria and decide when the criteria must change. Decisions then flow back into the risk documents, where auditors look for them.
| Decision in the minutes | Where the auditor looks for it next |
|---|---|
| Fund or bring forward a treatment, such as multi-factor authentication | The treatment plan, with owner and date; later, the working control |
| Add, withdraw or change a control | A revised Statement of Applicability with its justification, traced to the treatment decision |
| Tolerate a risk above the criteria for a period, or revise the criteria | The risk owner's dated acceptance, or the approved change to the risk method |
| Bring a new service, site or cloud region into scope | The revised scope statement, a risk assessment of the addition and, once certified, notice to the certification body |
| Change a policy, an objective or a role | The issued policy, objectives record, role description or training record |
Our risk assessment and treatment guide and Statement of Applicability guide cover the method itself.
The record auditors ask for
Clause 9.3.3 requires documented information as evidence of the results. That means minutes, backed by the pack they cite, showing:
- the date, with top management present rather than represented;
- every input addressed, citing the data or document version, even where nothing changed;
- decisions worded as decisions, under improvement and changes to the ISMS;
- an owner and a due date for each action, and the status of the last review's actions.
Auditors then trace a decision, such as a funded treatment, into the plan and the working control, and ask the chief executive what the last review decided; a clear answer without notes is strong evidence. Under ISO/IEC 17021-1, Stage 1 checks that reviews are planned and performed and every surveillance audit covers management review; our Stage 1 and Stage 2 guide explains the sampling.
What a weak management review looks like
In our gap analyses, weak reviews usually share one cause: the ISMS is treated as IT's system, so the review becomes an IT meeting with a leader's signature added later.
- The security team reviewing itself. The ISMS lead and IT staff meet; the managing director signs a week later. To an auditor, top management reviewed nothing.
- Risk mentioned, not reviewed. The minutes say "risks discussed", with no register version, late treatment or accepted residual risk on record.
- A 2013 agenda. Old templates omit changes in interested parties' needs, so new contract clauses and regulator expectations never reach leadership.
- Counts without trends. Thirty-eight incidents, with no comparison, cause or decision, tell leadership nothing.
- Actions that never close. The same item carried forward, review after review, without a new date or escalation.
- One staged review. A single meeting just before Stage 1, and none after certification, reads as a system built for the certificate.
How Effivity records the review
In Effivity's Management Review module you set the agenda or use Effivity's suggested one, attendees are e-mailed automatically, minutes sit against each agenda point and decisions become action plans, so next quarter's status comes from the same record. Presenters draw on modules such as Risk Management, Statement of Applicability, Incident Management and Internal Audit. Effivity is included with the engagement, at no additional cost, and is used in 50+ countries; see the Effivity guide.
How Sterling prepares your management review
A review your leadership will hold every quarter, with a record an auditor can follow.
Sterling's expert and experienced consultants agree the calendar with your leadership, give each input an owner and set up the pack, minutes and action log in Effivity. We facilitate the first review after the internal audit and before the Stage 1 readiness review, check its record against an auditor's questions, and keep the cycle running under Sustain™. We ensure successful certification for our clients. An independent, accredited certification body audits the ISMS and issues the certificate; Sterling does not certify.
Book a free discovery callISO/IEC 27001 management review: questions buyers ask
Must top management accept every residual risk itself?
No. Risk owners approve the treatment plan and accept what remains. The review sees those acceptances, tests them against the risk criteria and decides whether the criteria, or any acceptance, should be revisited.
How many reviews should we complete before the certification audit?
The standard sets no number. Stage 1 checks that reviews are planned and under way, and certification bodies generally expect one complete review before Stage 2. Hold it after the internal audit so its findings feed in; see our internal audit guide.
What if a serious incident happens a month after the review?
Do not wait. Incident response and corrective action run as usual, significant change triggers a fresh risk assessment, and top management can meet on anything urgent; the next review records what happened and what changed.
Can the review be held by video call, or by circulating the pack?
Video is fine; the standard requires a review, not a room. Circulating a pack rarely produces decisions; if you must, record each leader's response and the chair's consolidated decisions.
Should the information security policy be re-approved at every review?
No. Clause 5 has top management set the policy, and the Annex A control on information security policies expects review at planned intervals and after significant change. Confirm it yearly at the review and record any change as a decision.
More ISO/IEC 27001 guides
Every guide in the ISO/IEC 27001 series is written for one question and links back to the hub for the whole picture.
- Annex A: the 93 controls by theme, explained
- ISO/IEC 27001 certification cost: what moves the price
- ISO 27001 certification in India
- Integrating ISO/IEC 27001 with ISO/IEC 27701 and ISO 22301
- ISO/IEC 27001 internal audit: planning, conduct and reporting
- ISO 27001 certification in the Netherlands and Europe
- ISO/IEC 27001 nonconformities
- ISO/IEC 27001 for professional and legal services
- ISO/IEC 27001 requirements explained, clause by clause
- ISO/IEC 27001 risk assessment and treatment, step by step
- The Statement of Applicability: how to write one that survives the audit
- ISO/IEC 27001 vs SOC 2: which one, or both?
Keep exploring
Explore more about ISO/IEC 27001
Watch a video on how to implement ISO 27001 here.
Watch a video on ISO 27001 requirements here.
ISO/IEC 27001 resources
Services for ISO/IEC 27001
Talk to a consultant
Plan your ISO/IEC 27001 certification with confidence.
Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.
hello@sterling-grc.com+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page
What would you like to achieve?
Choose a starting point. The enquiry form takes about a minute.
Book my free discovery callContinue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice