Clause by clause: ISO 9001:2026 requirements: every clause explained →
What the certification body's auditor checks at the Stage 1 readiness review and at the Stage 2 audit, how a typical Stage 2 runs from opening meeting to closing meeting, how evidence is sampled and findings are raised, and who takes the certification decision.
Key points
- Stage 1, the certification body's readiness review, checks your documented information, scope, site, internal audit and management review. Stage 2 tests, at your site, whether the system is implemented and effective.
- ISO/IEC 17021-1, which accredited certification bodies must follow, requires both stages for an initial certification.
- Stage 2 follows a plan agreed in advance: opening meeting, top management, process audits on samples the auditor chooses, closing meeting.
- Nonconformities are written against a specific requirement, with evidence, and discussed with you. The auditor recommends; people at the certification body who were not on the audit decide.
What each stage checks
At Stage 1 the auditor asks whether your quality management system is ready to be audited. At Stage 2 the auditor asks whether it works: whether what you planned is done across the whole scope and delivers the results you set.
Both stages are required by ISO/IEC 17021-1, the international standard for bodies that audit and certify management systems, against which accreditation bodies assess certification bodies. That is why accredited bodies in Manila and London run an initial ISO 9001 audit on the same pattern. Selecting a body is covered in choosing an ISO 9001 certification body, and the full route to the certificate in the certification process guide.
Stage 1: the readiness review
ISO/IEC 17021-1 sets out what Stage 1 must achieve. Read as a checklist, it tells you what the auditor will ask for.
| Stage 1 objective | In an ISO 9001 system | Have ready |
|---|---|---|
| Review documented information | Scope, policy, objectives, process interactions, required documented information | Current approved versions with owners |
| Evaluate site conditions and preparedness | Premises, operations, shifts, off-site work | Access to all areas; process owners on hand |
| Review your understanding of the requirements | How quality is measured and objectives tracked | Objectives with targets, results and owners |
| Obtain scope information, including statutory and regulatory requirements | Whether the certificate wording matches what you do | Sites, activities and applicable legal requirements identified |
| Agree Stage 2 resources and details | Dates, sites, shifts, interviewees | Diaries of managers and process owners |
| Evaluate internal audits, management reviews and readiness | Audit programme and reports; review record | Completed reports and minutes, not only a schedule |
The certification body must tell you beforehand which Stage 1 activities will be on site; site conditions are hard to judge from documents, so expect some time at your premises. Stage 1 ends with documented conclusions on your readiness and any areas of concern that could become nonconformities at Stage 2. It is not a gap analysis: the auditor names concerns but does not design the fix.
Between the stages
The certification body must take your need to resolve those concerns into account when setting the interval, and may revise its Stage 2 arrangements because of them. Close each with evidence. You receive the audit plan and the names of the audit team in advance, and the dates are agreed with you; a valid objection to a team member obliges the body to reconstitute the team.
Stage 2: implementation and effectiveness
Stage 2 evaluates implementation, including effectiveness, at your site or sites. ISO/IEC 17021-1 requires it to cover at least:
- conformity with all the ISO 9001 requirements within your scope;
- monitoring, measuring, reporting and review of performance against key objectives and targets;
- meeting applicable statutory, regulatory and contractual requirements;
- operational control of your processes;
- internal audit and management review;
- management responsibility for your policies.
Effectiveness is the difference. A followed procedure shows implementation; a process that achieves its planned results, or whose shortfalls are noticed and acted on, shows effectiveness. Auditors test it by following consequences: a complaint to its corrective action and on to whether the problem returned.
A typical Stage 2, day by day
The certification body sets Stage 2 audit time from your effective personnel, process complexity and sites, under accreditation rules; the cost guide explains those drivers. This illustration assumes three days, one auditor and one site; your audit plan sets the real order.
| When | What happens | Who is needed | What is sampled |
|---|---|---|---|
| Day 1, start | Opening meeting: scope and plan confirmed; grading, communication, confidentiality and safety arrangements | Management, process owners, guides | The plan and changes since Stage 1 |
| Day 1, morning | Top management: context, policy, objectives, risks and opportunities, resources, management review | Senior manager in scope; quality coordinator | Objectives and results, review minutes, Stage 1 concerns closed |
| Day 1, afternoon | Customer processes: enquiries, quotations, contract review, changes | Sales and customer service | Orders picked by the auditor |
| Day 2, morning | Operations at the point of work: planning, delivery, inspection, release | Supervisors and operators | Instructions in use, inspection records, nonconforming output |
| Day 2, afternoon | Purchasing, suppliers, design if in scope, measuring equipment | Purchasing, engineering, maintenance | Supplier evaluations, design reviews, calibration |
| Day 3, morning | Competence, complaints, corrective action, customer satisfaction, internal audit | HR, quality coordinator, internal auditors | Training records, complaint files, proof that corrective actions worked |
| Day 3, afternoon | Auditor prepares conclusions; closing meeting | Management and process owners; attendance recorded | Findings, grading and deadlines presented |
Top management comes first because policy, objectives and management review frame everything else; if leadership cannot explain the system's purpose, each process audit tends to find the same gap. Each auditor normally has a guide from your side, and observers must be agreed with the certification body beforehand.
How auditors sample the evidence
ISO/IEC 17021-1 requires evidence to be gathered by appropriate sampling and verified through interviews, observation of processes and activities, and review of documents and records. In practice:
- The auditor chooses the sample from lists you provide: orders, complaints, suppliers, training records.
- Trails cross departments, from enquiry to invoice, because problems collect at the hand-offs.
- Answers are checked against records and, where possible, the work itself.
Sampling cuts both ways: a clean audit does not prove every process conforms, and one finding does not condemn a whole process. For multi-site organisations, accreditation rules also govern which sites are visited. The questions auditors typically put are in our audit questions guide.
How findings are raised
A nonconformity is recorded against a specific requirement of ISO 9001, with a clear statement of what is wrong and the objective evidence behind it. The auditor discusses it with you to confirm the evidence is accurate and understood; that is the time to produce a record the auditor has not seen, not to bargain over the grade. The auditor must not suggest the cause or the solution, a restraint that protects the certificate's impartiality.
- Major nonconformity: affects the capability of the system to achieve its intended results.
- Minor nonconformity: does not affect that capability.
- Opportunity for improvement: not a nonconformity, recorded where the scheme allows, and never a way to soften one.
Differences the audit team leader cannot resolve are recorded and referred to the certification body. Closing nonconformities is covered in our nonconformities guide.
The closing meeting, the report and the decision
The closing meeting presents the conclusions, including the recommendation on certification. You must also be told that the evidence came from a sample, how findings are reported and graded, how nonconformities affect certification, the deadline for your correction and corrective action plan, the certification body's next steps, and how complaints and appeals work. The written report belongs to the certification body; it states whether the system conforms and is effective, records unresolved issues and carries the recommendation.
The recommendation is not the decision. Competent people at the certification body who did not conduct the audit decide, after confirming that the audit information is sufficient, that corrections and corrective actions for every major nonconformity have been reviewed, accepted and verified, and that plans for minor ones have been accepted. A major nonconformity not verified within six months of the last day of Stage 2 means another Stage 2. Certification then starts a three-year cycle, covered in our surveillance and recertification guide.
How Sterling prepares you for both stages
No surprises at Stage 1, and a Stage 2 your people can explain.
Before the certification body arrives, Sterling's consultants run the internal audit and management review with your team, test your documented information against the Stage 1 objectives and close every finding with evidence. Records sit in Effivity, included with the engagement at no additional cost, so any sample can be produced without a search. We ensure successful certification for our clients. The audit and the certification decision belong to the independent, accredited certification body; Sterling does not certify.
Book a free discovery callStage 1 and Stage 2 audits: questions buyers ask
Can Stage 1 and Stage 2 happen in the same visit?
Some certification bodies schedule them back to back for small organisations with simple processes. A Stage 1 concern then has no time to be fixed, and Stage 2 may have to be rearranged. Unless your system is plainly ready, leave a few weeks between them.
Will the auditor tell us how to fix a nonconformity?
No. The auditor describes what is wrong and the evidence, but may not suggest the cause or the remedy. Root cause and corrective action are your organisation's work; the certification body judges whether your response is acceptable.
Can we challenge a finding?
Yes, on the evidence: raise it when the auditor discusses the finding and bring the record that changes the picture. Unresolved differences are recorded and referred to the certification body, whose appeals process remains open to you.
Can Stage 1 be carried out remotely?
Partly, where the certification body's procedures and the accreditation rules on remote auditing allow. The body must tell you in advance which activities will be on site, and site conditions, one of the things Stage 1 must evaluate, are hard to judge from a screen.
If Stage 2 finds no nonconformities, is the system proven?
It is a strong result, not a guarantee. The audit was a sample, and the certification body must say so. Use your internal audits to probe the areas the certification auditor saw least of.
More ISO 9001 guides
Every guide in the ISO 9001 series is written for one question and links back to the hub for the whole picture.
- ISO 9001:2026: what changes and how to transition
- ISO 9001 certification process, step by step
- ISO 9001 certification cost: what moves the price
- ISO 9001 documentation: what you need and what you do not
- ISO 9001 internal audit: planning, conduct and reporting
- ISO 9001 requirements explained, clause by clause
- ISO 9001 scope
- ISO 9001 certification in Singapore and South East Asia
- ISO 9001 for small businesses
- ISO 9001 surveillance and recertification
- ISO 9001 for technology and software
- The 2026 ISO Certification Plan
Keep exploring
Explore more about ISO 9001
Watch a video on how to implement ISO 9001 here.
Watch a video on ISO 9001 requirements here.
ISO 9001 resources
- ISO 9001:2026 transition serviceGap analysis to transition audit, by 30 September 2029
- ISO 9001 + ISO 14001 2026 transitionBoth standards in one coordinated programme
- ISO 9001 implementation planBuild your phased plan in the free Project Plan Generator
- ISO 9001:2026: what changes and how to transitionFor organisations certified to the 2015 edition
- Sterling Academy: ISO 9001 Awareness e-learningComing soon: view the course
Services for ISO 9001
Talk to a consultant
Plan your ISO 9001 certification with confidence.
Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.
hello@sterling-grc.com+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page
What would you like to achieve?
Choose a starting point. The enquiry form takes about a minute.
Book my free discovery callContinue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice