ISO 45001 guide
ISO 45001 contractor management: prequalification, induction, permits and the records auditors test
Clause by clause: ISO 45001:2018 requirements: every clause explained →
How ISO 45001 brings contractors under control through procurement: tiered prequalification, inductions and task briefings, permits to work for high-risk tasks, supervision, incident handling and close-out, with a worked example and the records auditors follow on a live job.
Key points
- ISO 45001 contractor management runs as one chain: select the contractor, induct its people, control the high-risk work with permits, supervise it, then close the job out and feed the result back into the next selection.
- The standard places contractors under Procurement (8.1.4), and its definition of a worker covers anyone working under your control, so contractor crews are part of your system.
- Prequalification should scale with the risk of the work: a cleaning contract and a confined-space entry do not need the same questionnaire.
- Auditors test the chain on the floor. They pick a live contractor job and ask for the prequalification file, the induction record, the permit and the supervisor's checks for that job.
Where contractor management sits in ISO 45001
ISO 45001:2018 deals with contractors in clause 8, Operation, under 8.1.4 Procurement. That clause has three parts: a general part, 8.1.4.2 Contractors and 8.1.4.3 Outsourcing. The placement makes sense: the risk is largely set when a contractor is chosen and the job specified.
The second anchor is the definition of a worker: a person performing work or work-related activities under the control of the organisation. Consultation and participation (5.4), awareness (7.3), the hierarchy of controls (8.1.2) and incident investigation (10.2) therefore reach contractor staff as well as employees.
Whether contractors and agency staff sit inside the boundary of the certificate is a scoping decision, explained in ISO 45001 scope: sites, workers, contractors and the mistakes that cost you. This guide assumes they do and deals with how you control them.
Prequalification: choosing contractors who can work safely
Prequalification is the check made before a contractor is approved for a type of work: enough evidence to judge that this firm can do this job safely. Tiers work better than one questionnaire for every supplier, and the work decides the tier, not the contract value.
| Tier of work | Typical examples | What to ask for before approval |
|---|---|---|
| Low risk | Office cleaning, catering, deliveries to a marked bay | Basic safety arrangements, insurance, agreement to follow site rules and the induction |
| Medium risk | Routine maintenance, landscaping, installation of equipment with hand tools | Task risk assessments, training records for the crew, incident history, the name of the person in charge on site |
| High risk | Work at height, hot work, confined spaces, electrical isolation, lifting operations, demolition | Method statements for the task, evidence of competence for each licensed or specialist role, equipment inspection records, incident history with investigations, how they control their own subcontractors |
Two points make prequalification credible at audit. First, someone competent reviews the answers and records the decision, including any conditions such as closer supervision for the first job. Second, the approved list has an expiry: a contractor approved years ago on documents that have since lapsed is not approved in any meaningful sense. Subcontractors face the same questions, and the contract should say so.
Induction and task briefing before work starts
Approval is about the firm; induction is about the individuals who turn up. A site induction covers site hazards, emergency arrangements, reporting routes and site rules; it is given to each person, recorded by name and repeated periodically.
The induction is also where a contractor worker should hear, plainly, that they can remove themselves from a situation they believe presents imminent and serious danger, and how to report a hazard, a near miss or a concern.
A task briefing then follows for the specific job: the method statement, the permit conditions, interfaces with your own operations, and who to call. Deliver both in a language the crew understands. An auditor who asks a contractor to explain the emergency route will soon find out whether that happened.
Permits to work and supervision of high-risk tasks
A permit to work is the written control that authorises a defined high-risk task, at a defined place and time, once named precautions are in place. Permits for high-risk tasks are among the most common pieces of ISO 45001 evidence, yet the standard does not prescribe a permit format, so the system has to fit your hazards.
A permit that works in practice has a small number of features:
- a clear list of tasks that need one, such as hot work, confined space entry, work at height above a set threshold, electrical and mechanical isolation, excavation and lifting;
- an issuer who is trained and authorised, separate from the person doing the work;
- precautions chosen in the order of the hierarchy of controls, with elimination and engineering measures before permits lean on personal protective equipment;
- checks at the workplace before signing, at set intervals and at shift change, with a handover when the job passes to a new crew;
- formal hand-back and close-out, confirming the area is safe and isolations are removed.
Supervision is the other half. Someone from your side checks that the method statement is followed, permit conditions hold and the crew is the one inducted. When the job changes in a way nobody planned, the management of change arrangements in 8.1.3 apply to contractor work as they do to your own.
Monitoring, incidents and close-out
Contractor incidents and near misses go into the same reporting system as your employees' and are investigated the same way, with the people involved taking part. Where the root cause lies in how the job was specified, prequalified or permitted, the corrective action belongs to you, not only to the contractor.
A short performance review at the end of a significant job closes the loop and updates the approved list. Repeated permit breaches mean conditional approval or removal. Contractor performance also belongs in the inputs to management review, which is covered in ISO 45001 management review: inputs, outputs and the record.
Auditors tour the workplaces during the certification audit. Contractor personnel under your control also count in the effective headcount used to set audit time, and a large temporary contractor presence is one of the factors that can add days, so expect the certification body to look for contractors on site and follow a job through its records.
A worked example: replacing a roof fan at a distribution centre
The example below follows one medium-sized job through the chain. It is illustrative, not a client case.
| Stage | What happens | Record kept |
|---|---|---|
| Specify | Facilities defines the job: remove and replace a roof extraction fan, with roof access and electrical isolation | Job scope with hazards identified at request stage |
| Prequalify | Contractor assessed at the high tier for work at height and isolation; crew competence and lifting equipment checked | Prequalification decision with reviewer's name and expiry |
| Plan | Method statement reviewed; edge protection chosen over harnesses where the roof allows; lift plan for the fan | Approved method statement and lift plan |
| Induct and brief | Each crew member inducted; task briefing on isolation points, forklift routes below and the emergency plan | Induction and briefing records by name |
| Permit | Work-at-height and isolation permits issued after checks at the roof and the switch room; one issuer coordinates both | Signed permits with isolation lock record |
| Supervise | Supervisor checks edge protection and exclusion zone below at start and after lunch | Inspection notes with the action closed |
| Close out | Isolation removed, permits handed back, roof and area inspected; performance review completed | Closed permits and contractor evaluation |
Where contractor controls break down
- Paper prequalification. Questionnaires collected, never assessed, never renewed.
- One questionnaire for everyone. High-risk trades pass on the same checklist as caterers.
- Inducting the supervisor, not the crew. The people on the tools never hear the site rules.
- Permits signed in the office. Nobody checks the precautions at the workplace before work starts.
- Invisible subcontractors. The approved firm sub-lets the job and nobody knows who is on the roof.
- Contractor incidents kept outside the system. Near misses go to the contractor's head office and never reach your investigation or your risk assessment.
The hazards of the task itself are assessed as described in ISO 45001 hazard identification and risk assessment; the legal duties you share with contractors belong in ISO 45001 legal register and evaluation of compliance.
How Sterling sets up contractor management
Contractor controls that hold up on a live job.
Sterling's expert and experienced OH&S consultants map your contractor population with you, set risk tiers, prequalification criteria, induction content and a permit system sized to your hazards, then test it on real jobs before the certification body does. With Design™ your team builds the arrangements under Sterling's structure and coaching; with Drive™ Sterling consultants carry the agreed work alongside your facilities, procurement and site teams. Approved lists, permits and incidents are held in Effivity, included with the engagement, at no additional cost. We ensure successful certification for our clients; the certificate is issued by an independent, accredited certification body, as Sterling does not certify.
Book a free discovery callISO 45001 contractor management: questions buyers ask
Does ISO 45001 require a contractor prequalification questionnaire?
No specific form is required. The standard expects contractor selection and control under 8.1.4; a tiered questionnaire is simply the most common way to show that selection considered the safety of the work.
Can we rely on a contractor's own ISO 45001 certificate instead of prequalifying them?
It is useful evidence, not a substitute. Check it is genuine and its scope covers the work, then still induct, permit and supervise.
Who is responsible for a contractor's safety on our site: us or them?
Both, in different ways. The contractor manages its own people and methods; you control the site, the permits and the interfaces with your operations, and local law decides the legal split.
Do short visits, such as a courier or a one-hour repair, need the full process?
No. Low-risk visits can be covered by a short site briefing and escort, while any task on your permit list gets the full permit and supervision regardless of how long it lasts.
Should contractors take part in our safety committee or consultation?
Where contractors work under your control for long periods, including them is good practice.
What will the certification auditor ask about contractors?
Expect a request to follow one current contractor job: the approval decision, the induction records of the people on site, the permit and its workplace checks, and any incidents or observations raised.
More ISO 45001 guides
Every guide in the ISO 45001 series is written for one question and links back to the hub for the whole picture.
- ISO 45001 certification process, step by step
- Choosing an ISO 45001 certification body
- ISO 45001 common mistakes
- ISO 45001 for construction
- ISO 45001 contractor management: prequalification to permits
- ISO 45001 certification cost: what moves the price
- Do I need ISO 45001? A decision guide for contractors, plant operators and boards
- ISO 45001 documentation
- ISO 45001 hazard identification and risk assessment
- ISO 45001 internal audit: planning, conduct and reporting
- ISO 45001 legal register and evaluation of compliance
- ISO 45001 requirements explained, clause by clause
- ISO 45001 revision: what is changing and when
Keep exploring
Explore more about ISO 45001
Watch a video on how to implement ISO 45001 here.
Watch a video on ISO 45001 requirements here.
ISO 45001 resources
Services for ISO 45001
Talk to a consultant
Put contractor controls in place that stand up on a live job.
Tell us your goals, locations and target date. We’ll help you define the scope, timeline and next steps.
hello@sterling-grc.com+1 201 263 4443 (global headquarters) · your nearest office and its number are at the top of this page
What would you like to achieve?
Choose a starting point. The enquiry form takes about a minute.
Book my free discovery callContinue to the enquiry form to share your details. Please do not include passwords, sensitive personal information or confidential files. A Sterling consultant replies within one working day. Privacy notice